Basrah Main Stadium Construction Timeline
In the summer of 2010, we assisted 360 Architecture in designing the GFRP facade panels and connection brackets of the new 65,000 seat soccer stadium in Basrah. The fabrication process had to be reduced by 18 months in order to host the first match in 2013. Given that the panels measure about 100 feet, it takes about 4 months to create one mold. Hence, the number of molds required for GFRP panels had to be reduced from 10 to 5. We worked very closely with the 360 Architecture and with Bahrain based fabricator BFG to accomplish this goal.